top of page
CENTRAL HEBER WATER & SEWER
REPLACEMENT PROJECT

Updated 05/16/25 at 11:00 am

LATEST NOTICES (est. work schedule): 

​​As we near the end of the project, there are currently eight crews working in the following areas:

  • 100 S between Main St and 100 E: Sewer and water line replacement is scheduled to begin by the week of May 19th. Work will start from the West side moving East. 

  • 300 N and surrounding roads: Sewer and water line replacement work is ongoing and will continue through late-May.

  • 100 E to 600 E (between 200 & 100 N): Sewer and water line replacement is scheduled to begin by the week of May 19th.  Work will start from the West side moving East.

  • Center Street and 500 S (between Main St. & 100 E): Sewer and water line replacement work is ongoing and will continue through late-May.

*Please avoid streets marked “Local Traffic Only,” as asphalt has been removed and parking is not permitted.​

 

​​

 

 

 

 

 

 

 

 

 

 

 

 

All excavated roads will be pulverized and repaved with new asphalt by Fall 2025. The estimated paving schedule is as follows: 

  • Late May 2025

    • Center Street

    • 400 N and adjacent north/south streets down to 300 N

    • 500 S (between Main Street and 100 E)

    • 550 E to the 500 N intersection

  • Mid July 2025

    • 100 S

    • 100 N

    • 300 N and adjacent north/south streets down to 300 N

  • Early October 2025

    • 200 N and adjacent north/south streets down to 100 N (from Main Street to 100 E)

 

*Please note: This schedule is subject to change based on weather conditions and construction progress. Updates will be posted here as needed.

10_16_24, 5_02 PM Microsoft Lens(6).jpg

Image:  Sewer/Water Excavation near 300 S and Main | 10/16/2024

UPDATED WORK LOCATIONS
| Through May 19, 2025 |

Construction Phase 1C Detour Map

PROJECT DESCRIPTION

The city's water and sewer infrastructure in the Central Heber area has significantly exceeded its service life.  As such, necessary improvements essential to maintaining a safe and reliable water/sewer system for residents and businesses.  The main focus for Phase 1 of the replacement program includes the East side of Main Street within the Central Heber area, as well as a four block stretch of sewer replacement along 3rd West.

Construction Days / Times

  • Daylight Hours

  • Mon - Fri

  • Sat-Sun (only as necessary)

  • No holidays

Contact Public Information

Info Hotline: (435) 406-4910

(Press 1 for live assistance)

Document.jpg
pdf icon.png
pdf icon.png
pdf icon.png
irrigation-icon.webp
irrigation-icon.webp
  • Facebook
  • X
image.png

* Schedule subject to change based on weather and material delivery

IMG_5613.jpg
3_5_24, 7_35 PM Microsoft Lens(7).jpg
6_11_24, 3_33 PM Microsoft Lens(3)_edite
IMG_6849.jpg

Pressurized Irrigation (PI) Information:

  • Pressurized Irrigation will be turned ON for the season on Monday, April 28th, 2025.

  • Ditch/Flood Irrigation was turned ON for the season on Monday, May 5th, 2025.

If you have a new PI pipeline installed as a result of our project, you will need to apply for a permit to gain service.  Please fill out a form below and turn it into the Heber Public City Works office @ 749 W 300 S, 
Heber City, UT 84032​
​​​​

​​

​​​​​

  • ​​Work will continue along 300 N installing sewer and water main pipelines.  Once completed, crews will return to replace service lateral connections to the water meter or cleanout.  Pressurized Irrigation lines will continue to be the final major utility installed, along with fiber-optic cable in prescribed locations.

  • Water Disconnect Notices: Be prepared for planned water disconnections within active construction zones.  You will receive 24-48 hr. notice.  Water outages should last from approximately 9am to 6pm.

Landscaping Restoration:

snip.png

Any outstanding surface vegetation restoration regarding phase 1C-1 (construction done in late 2024 and Spring 2025) will be completed as material arrives.  New work that starts in Spring and Summer 2025 will see surface vegetation restoration by end of Fall 2025.  Any emergent repairs to irrigation lines on private property will be addressed on request. If you have immediate needs, contact our hotline. 

3_5_24, 7_35 PM Microsoft Lens.jpg
image.png
Contact Us

Jeffrey Putzke

Public Information Manager

Sunrise Engineering

 

Phone:

(435) 406-4910

Email:

heberproject@heberut.gov

Message successfully delivered!

JeffPutzke.jpg
bottom of page